http://embeds.audioboom.com/publishing/p...Breakfast.
Dennis Latham on the BJCC board was interviewed at the beginning of hour 3 on the Leyland show.
Indicated a stadium opening of Spring 2021. Others have indicated an opening of fall 2020. Not sure which one is correct.
|
|
03-27-2018 10:39 PM |
|
iam4uab
All American
Posts: 4,702
Joined: Jul 2007
Reputation: 45
I Root For: UAB
Location: Wilmington, NC
|
RE: BJCC Board Member Interview
If true, it makes me feel good about the future with Coach Clark. I mean, I understand that money talks and all, but surely he'll want the satisfaction of running a team through that tunnel to, I would assume, a sold out crowd for the first true home field experience UAB football has ever had. Heck, by that time, we may be legitimately talking about moving into a better league.
|
|
03-27-2018 11:18 PM |
|
WesternBlazer
Hall of Famer
Posts: 22,195
Joined: Jan 2008
Reputation: 90
I Root For: UAB
Location:
|
RE: BJCC Board Member Interview
I always thought approximate stadium construction time is 2 years from 1st shovel to opening day. Of course, with so much other stuff going on at the same time, there could be a myriad of issues to work through. AB could probably shed more light on this...
|
|
03-27-2018 11:43 PM |
|
BlazintheATL
All American
Posts: 3,870
Joined: Jun 2007
Reputation: 25
I Root For: UAB
Location:
|
RE: BJCC Board Member Interview
I don't see how it could be ready by 2020. The earliest I can see construction beginning is late this year or early next year and from that point I think it will take at least two years.
|
|
03-28-2018 12:06 AM |
|
UAB Band Dad
Occasionally Reasonable
Posts: 24,437
Joined: Dec 2004
Reputation: 277
I Root For: A Free UAB!
Location:
|
RE: BJCC Board Member Interview
They were talking about groundbreaking this summer to early fall. Add two years.
|
|
03-28-2018 12:41 AM |
|
blazerball25
Special Teams
Posts: 764
Joined: May 2006
Reputation: 2
I Root For: UAB
Location: Dallas, TX
|
RE: BJCC Board Member Interview
OOC schedule for 2021 is:
09/11 - at Georgia
09/25 - at Tulane
10/02 - Liberty
We have an opening for the first week of that season. Would sure be nice to have a hard sellout against a big name opponent on 9/4/2021. Heck, even Alabama State or Alabama A&M would sell it out.
|
|
03-28-2018 07:21 AM |
|
imjustafatkid
Special Teams
Posts: 794
Joined: Aug 2014
Reputation: 6
I Root For: Bama/UAB/UNA
Location:
|
RE: BJCC Board Member Interview
(03-28-2018 07:21 AM)blazerball25 Wrote: OOC schedule for 2021 is:
09/11 - at Georgia
09/25 - at Tulane
10/02 - Liberty
We have an opening for the first week of that season. Would sure be nice to have a hard sellout against a big name opponent on 9/4/2021. Heck, even Alabama State or Alabama A&M would sell it out.
I'm hoping they can get it done in time for at least part of the 2020 season. If they break ground this summer, like some have said, it wouldn't be totally out of the realm of possibility for this to be done by the start of that season.
|
|
03-28-2018 07:34 AM |
|
the_blazerman
Legend
Posts: 30,397
Joined: Nov 2004
Reputation: 95
I Root For: UAB
Location:
|
RE: BJCC Board Member Interview
It was mentioned roughly 2 years from ground breaking.
|
|
03-28-2018 07:47 AM |
|
mixduptransistor
Hall of Famer
Posts: 10,987
Joined: Dec 2006
Reputation: 79
I Root For: UAB
Location: Atlanta
|
RE: BJCC Board Member Interview
there's a lot of variables and some levers they can pull to try to hit a certain date. I think a big target for them is the world games which is july 2021
they got regions field up and running on a pretty quick timeline, so it's not impossible.
|
|
03-28-2018 08:15 AM |
|
WesternBlazer
Hall of Famer
Posts: 22,195
Joined: Jan 2008
Reputation: 90
I Root For: UAB
Location:
|
RE: BJCC Board Member Interview
There's a $10 million bonus paid to the company that's rebuilding the interstate through downtown Birmingham to finish by a certain date. Hmmm...
|
|
03-28-2018 08:28 AM |
|
WesternBlazer
Hall of Famer
Posts: 22,195
Joined: Jan 2008
Reputation: 90
I Root For: UAB
Location:
|
RE: BJCC Board Member Interview
(03-28-2018 09:20 AM)ATTALLABLAZE Wrote: 2021 is correct. It will be a condensed design process to get a ground breaking this year unless they do a Design Build or just design the foundations first. People do not understand the process and how much work that goes into the design aspect.
After what happened at FIU recently...
|
|
03-28-2018 09:32 AM |
|
rook360
All American
Posts: 4,478
Joined: Oct 2007
Reputation: 64
I Root For: UAB
Location:
|
RE: BJCC Board Member Interview
(03-28-2018 09:32 AM)WesternBlazer Wrote: (03-28-2018 09:20 AM)ATTALLABLAZE Wrote: 2021 is correct. It will be a condensed design process to get a ground breaking this year unless they do a Design Build or just design the foundations first. People do not understand the process and how much work that goes into the design aspect.
After what happened at FIU recently...
I'd rather it be done right, than be done fast. We have a new stadium to play in. Let the rest sort itself out.
|
|
03-28-2018 10:19 AM |
|
imjustafatkid
Special Teams
Posts: 794
Joined: Aug 2014
Reputation: 6
I Root For: Bama/UAB/UNA
Location:
|
RE: BJCC Board Member Interview
(03-28-2018 09:20 AM)ATTALLABLAZE Wrote: 2021 is correct. It will be a condensed design process to get a ground breaking this year unless they do a Design Build or just design the foundations first. People do not understand the process and how much work that goes into the design aspect.
I definitely don't know anything about design. Would designing the foundations first to get a jump start on the project be a bad idea?
|
|
03-28-2018 10:22 AM |
|
mixduptransistor
Hall of Famer
Posts: 10,987
Joined: Dec 2006
Reputation: 79
I Root For: UAB
Location: Atlanta
|
RE: BJCC Board Member Interview
(03-28-2018 09:20 AM)ATTALLABLAZE Wrote: 2021 is correct. It will be a condensed design process to get a ground breaking this year unless they do a Design Build or just design the foundations first. People do not understand the process and how much work that goes into the design aspect.
They have to have some kind of earth moving before the end of the year, or a lot of this money turns into a pumpkin
|
|
03-28-2018 11:02 AM |
|
Blzer4Life
Super Blazer Moderator
Posts: 8,335
Joined: Jan 2005
Reputation: 39
I Root For: UAB
Location: Cyberspace
|
RE: BJCC Board Member Interview
(03-28-2018 08:15 AM)mixduptransistor Wrote: there's a lot of variables and some levers they can pull to try to hit a certain date. I think a big target for them is the world games which is july 2021
they got regions field up and running on a pretty quick timeline, so it's not impossible.
^This
|
|
03-28-2018 11:02 AM |
|
BlazerGreen
All American
Posts: 4,655
Joined: Dec 2010
Reputation: 45
I Root For: UAB, Goals
Location:
|
RE: BJCC Board Member Interview
(03-28-2018 11:18 AM)ATTALLABLAZE Wrote: I dn't think FIU was a design issue first blush. Could be wrong and ma not privy to the info. That was a post tension slab spnning a long distance and I think we will find out over time it was an erection issue. You had a cable failure and the only thing that will cause that is damaging it either physically or indirectly with improper support.
BTW I speak from experience as I just erected two pedestrian bridges last year over a major highway.
After the FIU bridge and USA practice facility collapses, I want them to take the time to do it right. We've waited this long so waiting until '21 is no big deal
Any idea if we end up closer to 45k seats or 55k?